Search Virginia Mason News

For the Week of Nov. 3

Sign up to receive these updates by e-mail!

***ALERT***

Construction Site Safety Drill Tuesday, Nov. 4

  • At 1 p.m. on Tuesday, Nov. 4, we are planning to conduct a safety drill at the construction site involving the Seattle Fire Department. We expect three to four fire department vehicles, including a hook-and-ladder truck, a fire engine and an ambulance, to arrive at the site with flashing lights and sirens. The vehicles will park along Boren Avenue. The drill will last about an hour. We want all of our neighbors to be assured that this is only a drill. In the event the Seattle Fire Department is called to duty, we will reschedule the drill and keep you informed. 

Removal of Trees

  • This week, as part of the approved project plans, we will remove two trees located on Virginia Mason property along Seneca Street, just west of the construction site. The area is being cleared to make way for a connection structure between the addition and the existing hospital building.

Site Foundation Work Continues

  • Intermittent concrete pours will continue on Seneca and Boren throughout the week. Concrete trucks will begin pouring at 8 a.m. on Seneca and 9 a.m. on Boren. Seneca and Boren will be limited to one lane in each direction during the construction pours. Parking on the south side of Seneca also will be unavailable temporarily.

  • Steel deliveries for the foundation continue this week on Seneca and Spring streets. This work requires temporary parking restrictions on the north and south sides of Seneca (6 a.m. to 6 p.m. weekdays north side; 24 hours/seven days a week south side).

  • As work around the foundation evolves, our activities over the next few weeks will continue to focus on pouring footings, columns and walls, laying rebar, and installing piping and conduits.

  • From time to time, residents may hear an "air horn" from the site. The reason for the safety alert is to let workers in the construction hole know that a heavy load is about to be lifted across the site.

  • Check out our webcam at VirginiaMason.org/construction!

No Weekend Work Planned for Saturday, Nov. 1, and Sunday, Nov. 2.

Sidewalk and Street Closures

  • Spring Street — Spring and its north sidewalk between Boren and Terry avenues will be closed 24 hours a day. The south sidewalk will be open to pedestrians throughout the week. If additional work is required in the alley, a wooden pedestrian footbridge will be installed.

  • Boren Avenue — The westward southbound lane on Boren between Seneca and Spring will be closed during normal construction hours and will be open after construction hours. The sidewalk will be closed 24 hours a day.

  • Seneca Street — For the time being, the south sidewalk on Seneca between Boren and Terry will be closed. The north sidewalk will be open.

  • Parking Spaces — The four parking stalls west of Boren on only the south side of Seneca will continue to be closed to parking.

Commitment to Crane Safety

  • Virginia Mason and our work team are deeply committed to ensuring 100-percent safety for our neighbors and our team. Visit our dedicated Web page for tower-crane safety information and activities at VirginiaMason.org/construction.

  • You may also call our Construction hotline, (206) 341-1511, any time to leave questions or concerns. We also ask that you use this hotline as a way to report unusual activity on or around the site.

In Closing
Thank you for your patience throughout the construction period. We apologize for the inconveniences these activities may cause. As updated information becomes available, we will be sure to share it with you.

For more information about the addition, including an image and video gallery, please visit VirginiaMason.org/construction.

If you have any questions, comments or concerns about the construction activities, please contact:

Back to Search