Search Virginia Mason News

For the Week of July 21

Sign up to receive these updates by e-mail!

What's New

  • Tower Crane Update
    Virginia Mason and our work team are deeply committed to ensuring 100-percent safety for our neighbors and our team. As previously communicated, a tower crane is expected to be erected on the construction site within the next couple weeks, and we will implement a thorough safety and communications effort to keep you informed. At any time, if you have questions, please do not hesitate to contact us (contact information listed at the end of this Web page).

  • Mass excavation on the site is complete. This means the bulk of material has been hauled out of the hole, and shoring is also complete.

  • We will continue to pour concrete on a periodic basis to prepare for the building foundation. Lane and street closures are listed below.

  • We are preparing for the mat slab to be poured. This is a six-foot thick concrete slab that is the main support structure for the building. It will be done in three pieces, the first of which will be poured Friday, July 25.

  • Periodically next week, there will be steel-bar deliveries using the smaller, 50-ton crane that is now on site.

  • A new 180-ton crane was erected on Spring Street. This will remain on site until the tower crane is erected, then both the 180- and 50-ton cranes will be removed.

  • Parking spaces along the north, westbound lane of Seneca, which were previously closed, are now available for public use.


What to Expect This Weekend

There will be no work associated with the VM construction project for Saturday, July 18, or Sunday, July 19.

SDOT Boren/Madison Paving Project
Please note that evening work associated with the Seattle Department of Transportation's Boren Avenue/Madison Street paving project is planned for this weekend (July 18 and 19). This work will occur between 7 p.m. Friday, July 18, and noon Saturday, July 19. If you would like more information about this project, please see the following link:

http://www.seattle.gov/transportation/boren_madison_pave.htm


Sidewalk and Street Closures

  • Spring Street — Spring and its north sidewalk between Boren and Terry avenues will be closed 24 hours a day.

    The south sidewalk will be open to pedestrians throughout the week. If additional work is required in the alley, a wooden pedestrian footbridge will be installed over the alleyway to allow access and passage.

  • Boren Avenue — The westward southbound lane on Boren between Spring and Seneca will be closed during normal construction hours and will be open after construction hours. The sidewalk will be closed 24 hours a day.

  • Seneca Street — For the time being, the south sidewalk on Seneca between Boren and Terry will be closed. The north sidewalk will be open this week.

  • Parking Spaces — The four parking stalls west of Boren on only the south side of Seneca will continue to be closed to parking.

In Closing

Thank you for your patience throughout this construction period. We apologize for the inconveniences these activities may cause. As updated information becomes available, we will be sure to share it with you.

For more information about the addition, including an image and video gallery, please visit VirginiaMason.org/construction.

If you have any questions, comments or concerns about the construction activities, please contact:

Back to Search