For the Week of Dec. 22

Sign up to receive these updates by e-mail!

Weather Update

  • Construction work was slowed due to the inclement weather on Thursday, Dec. 18, and Friday, Dec. 19. 

Weekend and Holiday Work

  • There will be no weekend work Saturday, Dec. 20, or Sunday, Dec. 21.

  • Weather permitting, there will be work on the site Monday, Dec. 22, through the middle of the day Wednesday, Dec. 24. There will be no work Thursday, Dec. 25, or Friday, Dec. 26.

Site Foundation Work Continues

  • Intermittent concrete pours will continue on Seneca Street and Boren Avenue throughout the week. Concrete trucks will begin pouring at 8 a.m. on Seneca and 9 a.m. on Boren. Seneca and Boren will be limited to one lane in each direction during the construction pours. Parking on the south side of Seneca also will be unavailable temporarily.

  • Steel deliveries for the foundation continue this week on Seneca and Spring streets. This work requires temporary parking restrictions on the north and south sides of Seneca (6 a.m. to 6 p.m. weekdays north side; 24 hours/seven days a week south side).

  • Activities over the next few weeks will continue to focus on pouring footings, columns and walls, laying rebar, and installing piping and conduits.

  • Residents may hear an air horn on occasion. This is a safety alert to let workers know a heavy load is about to be lifted across the construction site.

  • Check out our webcam at www.virginiamason.org/construction.

Sidewalk and Street Closures

  • Spring Street - Spring and its north sidewalk between Boren and Terry avenues will be closed 24 hours a day. The south sidewalk will be open to pedestrians throughout the week. If additional work is required in the alley, a wooden pedestrian footbridge will be installed.

  • Boren Avenue - The westward southbound lane on Boren between Seneca and Spring will be closed during normal construction hours and open after construction hours. The sidewalk will be closed 24 hours a day.

  • Seneca Street - For the time being, the south sidewalk on Seneca between Boren and Terry will be closed. The north sidewalk will be open.

  • Parking Spaces - The four parking stalls west of Boren on only the south side of Seneca will continue to be closed to parking.

Commitment to Crane Safety

  • Virginia Mason and our work team are deeply committed to ensuring 100-percent safety for our neighbors and our team. Visit our dedicated Web page for tower-crane safety information and activities at www.virginiamason.org/construction.

  • You may also call our Construction hotline, (206) 341-1511, any time to leave questions or concerns. We also ask that you use this hotline as a way to report unusual activity on or around the site.

In Closing
Thank you for your patience throughout the construction period. We apologize for the inconveniences these activities may cause. As updated information becomes available, we will share it with you.

For more information about the addition, including an image and video gallery, please visit www.virginiamason.org/construction.

If you have any questions, comments or concerns about the construction activities, please contact:

Best wishes for a safe and happy holiday season!